Decision details

Programme Approvals

Decision Maker: Mayoral Combined Authority Board

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

That the Board considered: 

 

Project and Programme Approvals

1.     Progression of “Active Travel Bridges - Smithies & Dearne Valley” to post OBC in-principle approval and award £3.54m to Barnsley Metropolitan Borough Council subject to the conditions set out in Appendix A.

2.     Progression of “CRSTS and TCR Five-Year Revenue Programme” to full approval and onward award of £77.64m as detailed in section 1.1

3.     Progression of “Highways Capital Maintenance” to full approval and onward award of £68.1m as detailed in section 1.1

4.     Progression of “Tram life extension additional costs” change request.as detailed in section 1.1

 

Grant Acceptances:

5.     Acceptance and onward award of £0.65m “Skills Bootcamps Grant” from the Department of Work and Pensions as detailed in section 2.1

 

Funding Bids:

6.     Endorsed the submission of a proposal of to the Ministry for Housing, Communities and Local Government (MHCLG) for “Housing Accelerator Fund” and delegate authority to the Executive Director - Growth, Business and Skills, in consultation with the Section 73 and Monitoring Officer to accept and onward award any subsequent grant as detailed in section 2.1

7.     Endorsed the submission of a proposal of to the Department for Business, Innovation, Science and Trade (BSIST) for “Made Smarter additional grant” and delegate authority to the Executive Director - Growth, Business and Skills, in consultation with the Section 73 and Monitoring Officer to accept and onward award any subsequent grant as detailed in section 2.1

 

Delegations:

Delegated authority to the Head of Paid Service in consultation with the Section 73 and Monitoring Officer to enter into legal agreements for the points above 

Report author: Laurie Thomas

Publication date: 27/10/2026

Date of decision: 27/10/2026

Decided at meeting: 27/10/2026 - Mayoral Combined Authority Board