Decision Maker: Executive Director of Transport
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
To progress the Phase 1 scheme, it is
necessary to appoint a number of utility companies to carry out
diversion works for all existing services and equipment affected by
the highway works. Each company will require payment in advance,
based on detailed C4 estimates, in order to get them to
commit to the works and enable the Main Contractor to programme and
coordinate their individual on-site activities.
In accordance with Standing Order 5.8.1 (a) (i), the services are
proprietary, and no alternative provider is available.
These costs are refundable, should the scheme not proceed.
Zayo Group have submitted a C4 detailed estimate in the sum of
£81,585.29
Option 1 - Approve the appointment of Zayo
Group to carry out underground service diversions and associated
civil engineering works at a cost of £81,585.29 based on
detailed C4 stage estimate.
Option 1
Approve appointment of Zayo Group to carry out underground
diversion work – recommended.
Option 2
Do not approve appointment of Zayo Group – Without this work
being carried out, the scheme could not proceed.
Publication date: 01/06/2023
Date of decision: 31/05/2023
Accompanying Documents: