Decision Maker: Executive Director of Transport
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
The Meadowhall Mobility Hub and Car Park
Expansion scheme is included in the SYMCA City Region Sustainable
Transport Settlement (CRSTS) programme of schemes.
This appointment will facilitate the progression of the project
through the project stages until Stage 6 of the ACE schedule of
services (handover and closeout).
The scope for the consultant appointment includes various aspects
of technical support, including:
• Design;
• Planning;
• Transport Modelling;
• Business Case Support;
• Stakeholder liaison;
• The role of Principal Designer;
• Quantity Surveying;
• Project Administration;
• NEC Project Manager Services
Responses were received from 4 bidders. These bids were scored on
the basis of 60% price and 40% quality and Arup came out as overall
winner for the tender. As such, approval is requested to appoint
Arup at a total fee of £242,328 through the YORconsult2
framework.
Approval given to appoint Arup for the
Meadowhall Mobility Hub and Car Park Expansion Project at a total
fee of £242,328
1. Appointment of Arup
2. Do not appoint Arup
Option 1 is recommended as this will allow the CRSTS Meadowhall
Mobility Hub project to be progressed through the relevant stages.
Note, the appointment of a contractor to build the scheme would be
a separate appointment.
Publication date: 03/07/2024
Date of decision: 01/07/2024