Decision Maker: Executive Director of Transport
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Swarco was appointed as infrastructure
providers of the Rotherham Transport Interchange (RTI) and
Sheffield Transport Interchange ZEBRA projects, as part of a NEC4
contract through the TPPL framework. The original appointment was
for a total fee of £1,301,940.49.
A new substation is needed at RTI in order to power the two new
pantograph chargers. Following the Swarco appointment, it became
apparent that the optimal location for the new substation (in the
service yard close to the existing substation) wouldn’t be
possible, as this would require landlord approval, something which
became clear would be very difficult to obtain. As such, an
alternative site for the new substation has been located.
A change control relating to additional infrastructure works at
RTI, is outside the scope of the original Swarco commission. The
total of this change control is £314,131.
Approval is given to increase the value of
Swarco’s existing contract by £336,291
1. Approve the change control
2. Do not approve the change control
Option 1 is recommended as this will allow the progression of the
RTI substation and pantograph charger works. Without this, the
pantograph chargers will not work.
Publication date: 03/07/2024
Date of decision: 28/06/2024