Decision Maker: Executive Director of Transport
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Swarco were appointed as infrastructure
providers for Rotherham Transport Interchange and Sheffield
Transport Interchange as part of the South Yorkshire ZEBRA
projects. They were appointed based on a NEC4 contract through The
Procurement Partnership Limited (TPPL) framework.
As current contract costs exceed 10% of original commission total,
approval of a further £138,653.68, is requested for these
latest change controls.
Option 1 – Approve the increase in value
of Swarco’s existing contract by £138,653.68.
Option 1 - Approve the increase in value of
Swarco’s commission to allow the progression of the RTI works
to provide two pantograph chargers and associated new substation
works.
Option 2 - Do not approve the increase in value of Swarco’s
commission. This would result in further costs and delays to the
construction phase of the programme.
Publication date: 30/09/2024
Date of decision: 27/09/2024