Decision Maker: Executive Director of Transport
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: No
Between 2013 and 2015, embedded rail
replacement works were undertaken on the Supertram network. These
were carried out by Volker Rail to a design provided by South
Yorkshire Supertram Limited (SYSL).
Following these works, significant lengths of polymer installed by
Volker next to the rails failed leading to polymer
delamination.
At the PTT meeting on 31/08/22 a report recommended that SYMCA
procure and fund the necessary remedial works via a suitable
contractor under a form of call off contract for 4/5 years.
Following a market engagement exercise with the market, a set of
tender documents was issued in April 2023. Three tenders were
received. The scope of the works covers polymer replacement,
concrete repairs and associated traffic management.
Colas Rail Limited provided the tender with the most economically
advantageous solution, and in February 2024 SYMCA entered into a
Term Service Contract with Colas on a call-off basis, via discrete
Task Orders. Works covered under the first Task Order have been
delayed are currently nearing completion on site.
The second Task Order relates to works on Glossop Road and West
Street and Colas have provided a quotation of £1,539,616 to
undertake these works. Approval is sought for an amount which
includes a risk/contingency allowance i.e. £1,684,648.
It is also proposed to retain Mott Macdonald in the role of Service
Manager for the Task Order 2 works. The Service Manager role is a
combination of reviewing the Contractor’s programme and
methodology, observing the work on site, instructing the Contractor
where necessary, managing change and costs, and administering the
Contract. Full-time site attendance at night is provided as part of
the Service Manager role. Mott Macdonald have provided a quotation
of £224,398 to undertake the Service Manager role for the
Task Order 2 works on Glossop Road and West Street (including a
risk/contingency allowance).
Mott Macdonald have provided a quotation for a further
£62,572 to undertake the Service Manager role on the first
Task Order through to the revised completion date in the light of
the delays referred to above.
Approval is sought for the Mott Macdonald fees described above
(total value £286,970).
• Appoint Colas Rail Limited to undertake
the Task Order 2 works at a cost of £1,684,648.
• Appoint Mott Macdonald Limited to undertake the Service
Manager role at a cost of £286,970.
1. Do Nothing – this option would see no
remedial action undertaken leading to further loss of polymer, in
turn increasing the likelihood of a road traffic collision and
serious injury or fatality, which is clearly unacceptable
2. Appoint Colas Rail Limited to undertake the Task Order 2
works.
Publication date: 02/05/2025
Date of decision: 02/05/2025