Decision Maker: Executive Director of Transport
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
SYMCA has been working with Arup, Swarco and
Northern PowerGrid to deliver the pantograph charging
infrastructure at RTI. Unfortunately, delays to the implementation
of a new substation at the interchange has meant that the
pantographs are not yet in operation, and they are unlikely to be
in operation until the end of this financial year (current
forecast).
Rather than reduce service levels and provide a poorer service for
customers, including reputational risk for SYMCA, Stagecoach have
implemented an inefficient vehicle schedule to allow charging at
the depot.
Stagecoach have provided details that without the pantograph
chargers a number of buses have to be returned to depot. This
requires additional staff time as a direct result of the delays to
the SYMCA project. This report seeks approval to fund these
additional costs.
The funding approval required for this revenue cost is
£45,850.00 covering the additional costs until 31 August and
all the cost through to 01 March 2025. Previous approvals of
£17,000 (not part of this paper) take the final total
approval value to £61,950.00.
Further background information due commercially sensitive
information is redacted and included in the Transport Directorate
Leadership Team approval papers dated 12 November 2024.
Recommendations approved. Total cost of awards
is £45,850.00.
Previous approvals of £17,000 (not part of this paper) take
the final total approval value to £61,950.00
4.1 Do nothing (not recommended) – do
not fund the additional costs being incurred by Stagecoach as a
result of the SYMCA capital project being delayed. This could risk
reputational risk with Stagecoach, the DfT, partners and the public
if Stagecoach revert to using some diesel buses or reduce services
to accommodate the additional charging requirements.
4.2. Do something (recommended) – fund the additional costs
as outlined, noting that further delays to implement the charges
could require further funding. This maintains the current service
levels and does not cause the impacts outlined in 4.1
4.3. Do most (not recommended) – approve a dedicated revenue
funding stream to mitigate the impact of capital project delivery
on public transport operations.
Publication date: 10/01/2025
Date of decision: 11/12/2024
Accompanying Documents: