Use the below search options at the bottom of the page to find information regarding recent decisions that have been taken by the Combined Authority.
Alternatively you can visit the officer decisions page for information on officer delegated decisions that have been taken by officers with authority to take delegated decisions for the Combined Authority.
To fill management capacity following the
departure of the Chief Executive of the OPCC and a failed
recruitment exercise for an Executive Director of Policing &
Reform.
A candidate was needed at short notice with relevant experience of
working in the sector.
Following a shortlisting and interview process, David Peet was
selected to fulfil the interim role until 31 March 2025.
Decision Maker: Executive Director of Policy and Strategic Development
Decision published: 01/11/2024
Effective from: 16/09/2024
Decision:
Option 2. Appoint an interim resource to
undertake this role until the appointment of a permanent Director
of Policing & Reform is made.
Lead officer: Clare Monaghan
The Digital Infrastructure Team is a
partnership between the local authorities of Barnsley, Doncaster,
Rotherham, Sheffield, and the South Yorkshire Mayoral Combined
Authority. The existing team has been hosted by Barnsley Council
but it works on behalf of all partners. It was established in 2014
to improve the availability of digital infrastructure as superfast
broadband was rolled out.
The SY Digital Infrastructure Team is currently funded by SYMCA for
three years: 2022/23 – 2024/25 using Openreach superfast
contract clawback.
A Project Mandate form was considered by Programme Board (26th
September) highlighting the continued role of the digital
infrastructure team in delivering the South Yorkshire
Infrastructure Strategy. The Board supported extending funding of
the team for a further year (2025/26) during which a Business
Justification Case would be prepared considering longer-term
funding for the team in the context of the changing digital
environment.
In the interim, underspend from the existing contract was
recommended to extend funding for the SY Digital Infrastructure
Team (2.6xFTEs) for financial year 2025/26, proposed to be funded
from underspend against existing budget for 2022/23 to 2024/25 of
£148,593, plus additional funding of £28,665 to close
the funding gap:
Funding profile for 2025/26 £177,258 Staffing costs and
overheads at 15%
2022/23 – 2024/25 budget underspend £148,593 Source:
Openreach superfast contract clawback
Funding gap £28,665
The request was recommended for approval at the SYMCA Change Panel
on 23rd October.
Decision Maker: Section 73 Officer
Decision published: 31/10/2024
Effective from: 30/10/2024
Decision:
Option 1 – Approve the
recommendation
Lead officer: Gareth Sutton
In March 2023 the MCA board approved the
revised Assurance Framework. The revised Assurance Framework
provides for a one-stop governance process. This change was
designed to improve the pace at which schemes can be developed and
delivered. Strategic Business Cases are undertaken within
authorities with Outline Business Cases undertaken at MCA Board
level.
The Framework allows for schemes that are accepted into the
programme to access development funding. Development funding is a
key component in supporting the development of quality schemes at
pace and is distributed on conclusion of the Strategic Business
Case. Accordingly, there was an unintended discrepancy where the
intention for a one-stop process was undercut by the need to seek
separate approvals for development funding release and OBC
approvals.
Therefore, in July 2023 the MCA board granted approval to delegate
authority to the Head of Paid Service in consultation with
Portfolio Leaders and the Section 73 and Monitoring Officer to
approve the release of development cost funding in line with the
Assurance Framework to enable schemes to progress as efficiently as
possible.
Decision Maker: Section 73 Officer
Decision published: 29/10/2024
Effective from: 29/10/2024
Decision:
Option 1 – Approve the
recommendation
Lead officer: Gareth Sutton
In March 2023 the MCA board approved the
revised Assurance Framework. The revised Assurance Framework
provides for a one-stop governance process. This change was
designed to improve the pace at which schemes can be developed and
delivered. Strategic Business Cases are undertaken within
authorities with Outline Business Cases undertaken at MCA Board
level.
The Framework allows for schemes that are accepted into the
programme to access development funding. Development funding is a
key component in supporting the development of quality schemes at
pace and is distributed on conclusion of the Strategic Business
Case. Accordingly, there was an unintended discrepancy where the
intention for a one-stop process was undercut by the need to seek
separate approvals for development funding release and OBC
approvals.
Therefore, in July 2023 the MCA board granted approval to delegate
authority to the Head of Paid Service in consultation with
Portfolio Leaders and the Section 73 and Monitoring Officer to
approve the release of development cost funding in line with the
Assurance Framework to enable schemes to progress as efficiently as
possible.
Decision Maker: Section 73 Officer
Decision published: 29/10/2024
Effective from: 29/10/2024
Decision:
Option 1 – Approve the
recommendations
Lead officer: Gareth Sutton
The existing Gas Supply contract ends on 31st
March 2025.
In order to assess the most appropriate supplier for a new gas
supply contract a two part approach was undertaken and a report was
compiled.
See accompanying report document.
Part 1 – to determine if the new supply should be through a
public sector framework or through a private broker.
Part 2 – upon the decision that the outcome of the above was
to look to procure gas from a public sector framework. To determine
which framework was the most appropriate based on market prices,
service provision and social value.
The outcome of part 2 was that YPO scored the highest assessment
mark. It is therefore recommended to sign up with YPO for gas
supply from the 1st April 2025.
YPO is the current supplier of gas to SYMCA and has also supplied
electricity in the past. They have a large customer base within the
Yorkshire and Humber region of mainly public sector organisations,
including neighbouring councils in South Yorkshire and the OPCC.
YPO employ a team of energy specialists, which includes traders,
risk managers and energy specialists who work with YPO’s
designed supplier.
YPO’s gas frameworks are recognised as being fully compliant
with regards to OJEU and the Public Contracts Regulations 2015 and
the national Energy Strategy Team guidelines. Gas supplies are to
be obtained from a Contract which has been selected through tender
by YPO. The selected supplier is Corona.
The type of contract is a flexible contract where at least 80% of
the projected gas demand for SYMCA is purchased flexibly over a
period of 18 months prior to the contract start. Buying flexibly
ensures that the best purchase rates are achieved against market
fluctuations, allowing gas to be bought at opportune moments (such
as when the market is lower), avoiding market peaks to keep the
costs down. Buying gas in this manner generally results in a
significantly lower commodity cost than the industry average or
that which SYMCA would be able to achieve alone.
Not all the 100% of projected gas is bought prior to the supply
period, as noted above, so as to take account of any fluctuations
in demand for gas due to climatic temperatures that may mean less
gas is required than predicted. This avoids having to sell gas
commodity back to the grid at a loss.
The projected cost of the contract in the first year (2025/26),
based on existing gas usage and a current forecasted unit price of
3.8p/kwh (this will vary over the 4 years of the contract), will be
£78,000. (This includes all non-commodity charges.)
This contract is a 4+2+2 contract, so initially SYMCA would be
contracted to YPO for supply for 4 years, with 2 potential
extensions.
Decision Maker: Section 73 Officer
Decision published: 23/10/2024
Effective from: 23/10/2024
Decision:
That the Executive Director Resources and
Investment approve the purchase of gas via the Yorkshire Purchasing
Organisation (YPO) framework contract for the 4 years from 1st
April 2025.
There will then be the potential to enter into 2 further contract
extensions from 1st April 2029 and 1at April 2031 as noted
above.
Lead officer: Gareth Sutton