Use the below search options at the bottom of the page to find information regarding recent decisions that have been taken by the Combined Authority.
Alternatively you can visit the officer decisions page for information on officer delegated decisions that have been taken by officers with authority to take delegated decisions for the Combined Authority.
To agree to procure the services from
PROGRAMME & COMMERCIAL SERVICES LIMITED to provide a Programme
Lead consulting service through Martin Barnett (consultant) for the
Tram Asset Renewal project at an anticipated overall cost of
£90,000 plus £6,000 expenses.
Following the departure of the Senior Principal Project Manager,
there is currently a gap in overall responsibility for managing and
delivering the Tram Asset Renewal £100m investment
programme.
This role will champion a collaborative working environment to
build a robust and high performing team capable of rising to the
challenges of the programme and developing trusting relationships
and governance with peer groups and senior stakeholders.
The service provided will cover responsibility for all aspects of
the programme, including (but not limited to) scope setting,
resourcing and recruitment, procurement, operations, financial
management, progress monitoring and reporting, along with the
managing emerging risks and opportunities to ensure that the
desired outcomes and objectives are delivered within time, cost,
quality and scope targets.
Martin Barnett was originally recruited for the tram transition
work via a form of competition where he was one of two candidates
interviewed. Martin is therefore a known quantity when it comes to
Mass Transit, with the mobilisation/transition experience and
competence to be able to hit the ground running and effectively
continue provision of this type support to SYMCA.
It is anticipated that Martin would work (on average) 3 days per
week on the Asset Renewal project on a temporary and time limited
basis until 31 March 2025.
Decision Maker: Executive Director of Transport
Decision published: 15/08/2024
Effective from: 24/07/2024
Decision:
Option 3: To agree to enter into contract with
PROGRAMME & COMMERCIAL SERVICES LIMITED to provide Programme
Lead consulting services through Martin Barnett (consultant) for
the Tram Asset Renewal project at an anticipated cost of
£90,000 plus £6,000 expenses.
Lead officer: Pat Beijer
To agree to procure the services from
PROGRAMME & COMMERCIAL SERVICES LIMITED to provide a Programme
Lead consulting service through Martin Barnett (consultant) for the
Bus Reform project at an anticipated overall cost of £60,000
fees plus £4,000 expenses.
A bus franchise assessment is currently being undertaken and
reviewed, and a lead is required to take on responsibility for
managing the programme. Following the departure of the interim
Programme Director and the Enhanced Partnership Director on 1 April
2024, SYMCA has had no dedicated programme resource supporting the
Bus Reform programme. Existing resource deployed is not capable of
sustaining the level of time commitment this complex and critical
programme requires.
The role will champion a collaborative working environment to build
robust and high performing team capable of rising to the challenges
of the programme and developing trusting relationships and
governance with peer groups and senior stakeholders.
The service provided will cover responsibility for all aspects of
the programme, including (but not limited to) scope setting,
resourcing and recruitment, procurement, operations, financial
management, progress monitoring and reporting, along with the
managing emerging risks and opportunities to ensure that the
desired outcomes and objectives are delivered within time, cost,
quality and scope targets.
Martin Barnett is a known entity to SYMCA, as he was originally
recruited for the tram transition work via a form of competition
where he was one of two candidates interviewed, so he already knows
the organisation well and has the skill set required to effectively
provide this type support.
It is anticipated that Martin would work (on average) 2 days per
week (subject to further MCA decisions) on the Bus Reform project,
on a temporary and time limited basis until 31 March 2025. The
balance of time commitment is subject to change and to be informed
by future MCA decisions and the evolution of the
programme.
Decision Maker: Executive Director of Transport
Decision published: 15/08/2024
Effective from: 24/07/2024
Decision:
Option 3: To agree to enter into contract with
PROGRAMME & COMMERCIAL SERVICES LIMITED to provide Programme
Lead consulting services through Martin Barnett (consultant) for
the Bus Reform project at an anticipated cost of £60,000 fees
plus £4,000 expenses
Lead officer: Pat Beijer
Between 2013 and 2015, embedded rail
replacement works were undertaken on the Supertram network. These
were carried out by Volker Rail to a design provided by South
Yorkshire Supertram Limited.
Following these works, significant lengths of polymer installed by
Volker next to the rails failed leading to polymer
delamination.
In February 2024 SYMCA entered into a Term Service Contract with
Colas Rail Limited to undertake polymer replacement and concrete
track bed repairs (to deal with significant concrete defects at
sites identified for polymer replacement) on a call-off basis, via
discrete Task Orders. Colas’s tendered sum to undertake these
works for the first Task Order, which relates to a section of Park
Grange Road where the most significant polymer defects are located,
is £2,032,028.57. Approval of a figure of £2,194,590.85
(£2,032,028.57 plus 8% risk contingency) was granted at the
PTT meeting on 27/09/23.
The repair schedule on which Colas’s tender was based was
determined on the basis of a pre-tender survey carried out without
traffic management in place and whilst trams were running. These
constraints prevented a detailed close-quarters survey from being
carried out. Subsequent site surveys have identified significant
additional concrete repair work within the Park Grange Road site.
Specifically, a detailed survey was carried out by Colas and Mott
Macdonald, with traffic management in place, enabling defects to be
more accurately identified and recorded. The total revised
estimated cost of the works is £3,651,101.23.
The additional cost over and above the existing approved figure is
£1,456,510.38.
The additional defects identified in the concrete slab are all
considered to be significant and require prioritised repair. This
repair work is necessary to arrest further deterioration and
preserve the longevity of the track slab.
It is foreseeable that the defects in the concrete slab may cause
harm to road users, in particular cyclists and pedestrians. Having
a contractor mobilised for the type of works involved represents a
significant opportunity to mitigate this risk promptly.
SYMCA’s Rail Safety Officer advocates the inclusion of the
additional work in the current Task Order.
Decision Maker: Executive Director of Transport
Decision published: 09/08/2024
Effective from: 02/08/2024
Decision:
To instruct Colas Rail Limited to undertake
additional work on the South Yorkshire Supertram Embedded Rail
Repairs Contract, comprising additional repairs to the concrete
track slab identified in a site survey carried out post Contract
award, at a cost of £1,456,510.38 (including a 6% allowance
for risk).
Lead officer: Melanie Corcoran
The current management agreement that is in
place with Meadowhall shopping centre for the operation of the
interchange, requires the pedestrian bridge, linking the
interchange to the shopping centre, to be painted every 5 years. It
was last done in 2017.
The project was tendered to 4 contractors who had expressed an
interest. Of these 2 submitted tenders, Alfred Bagnall & Sons
Ltd and Coating services ltd. The returns have been assessed for
quality to ensure they pass the minimum standard required and meets
the specification required.
The tender assessment resulted in the following scores that were
assessed jointly with Ridge and partners who are acting as project
administrators.
Company Quality Price Total
Bagnalls 32.00% 60.00% 92.00%
CSL 23.20% 27.03% 50.23%
The work will therefore be undertaken by the successful tenderer,
Alfred Bagnall & sons ltd, for a price of
£84,888.30.
Decision Maker: Section 73 Officer
Decision published: 01/08/2024
Effective from: 31/07/2024
Decision:
Approved
Lead officer: Michelle Stansfield