Between 2013 and 2015, embedded rail
replacement works were undertaken on the Supertram network. These
were carried out by Volker Rail to a design provided by South
Yorkshire Supertram Limited.
Following these works, significant lengths of polymer installed by
Volker next to the rails failed leading to polymer
delamination.
In February 2024 SYMCA entered into a Term Service Contract with
Colas Rail Limited to undertake polymer replacement and concrete
track bed repairs (to deal with significant concrete defects at
sites identified for polymer replacement) on a call-off basis, via
discrete Task Orders. Colas’s tendered sum to undertake these
works for the first Task Order, which relates to a section of Park
Grange Road where the most significant polymer defects are located,
is £2,032,028.57. Approval of a figure of £2,194,590.85
(£2,032,028.57 plus 8% risk contingency) was granted at the
PTT meeting on 27/09/23.
The repair schedule on which Colas’s tender was based was
determined on the basis of a pre-tender survey carried out without
traffic management in place and whilst trams were running. These
constraints prevented a detailed close-quarters survey from being
carried out. Subsequent site surveys have identified significant
additional concrete repair work within the Park Grange Road site.
Specifically, a detailed survey was carried out by Colas and Mott
Macdonald, with traffic management in place, enabling defects to be
more accurately identified and recorded. The total revised
estimated cost of the works is £3,651,101.23.
The additional cost over and above the existing approved figure is
£1,456,510.38.
The additional defects identified in the concrete slab are all
considered to be significant and require prioritised repair. This
repair work is necessary to arrest further deterioration and
preserve the longevity of the track slab.
It is foreseeable that the defects in the concrete slab may cause
harm to road users, in particular cyclists and pedestrians. Having
a contractor mobilised for the type of works involved represents a
significant opportunity to mitigate this risk promptly.
SYMCA’s Rail Safety Officer advocates the inclusion of the
additional work in the current Task Order.
Decision type: Non-key
Decision status: Recommendations Approved
Notice of proposed decision first published: 09/08/2024
Decision due: 2 Aug 2024 by Executive Director of Transport
Contact: Melanie Corcoran, Executive Director of Transport Email: melanie.corcoran@southyorkshire-ca.gov.uk.