Issue details

Approval of additional costs on LRT Signal Heads Replacement project.

Refer to attached LRT Signal Heads Budget Increase paper.

Approval of an increase in cost from £395,801 to £522,767 is sought. The latter figure includes a 10% risk contingency on future project costs.



Decision type: Non-key

Decision status: Recommendations Approved

Notice of proposed decision first published: 29/01/2025

Decision due: 28 Jan 2025 by Executive Director of Transport

Contact: Melanie Corcoran, Executive Director of Transport Email: melanie.corcoran@southyorkshire-ca.gov.uk.