On 12th March 2024 MCA Board, the scheme
secured OBC in principle approval for up to £2m grant.
On 10th April 2024 SYMCA Programme Board, the release of
£0.28m development grant was approved.
On 6th March 2025 SYMCA Programme Board, the release of an
additional £0.5m development grant was approved.
In accordance with the SYMCA Assurance Framework, the SYMCA
Programme Board have delegated authority to approve development
grant to support progression of the business case/scheme.
Decision type: Non-key
Decision status: Recommendations Approved
Notice of proposed decision first published: 10/03/2025
Decision due: 10 Mar 2025 by Section 73 Officer
Contact: Gareth Sutton, Executive Director of Resources & Investment Email: Gareth.sutton@southyorkshire-ca.gov.uk Email: Gareth.Sutton@southyorkshire-ca.gov.uk.