To progress the Phase 1 scheme, it is
necessary to appoint a number of utility companies to carry out
diversion works for all existing services and equipment affected by
the highway works. Each company will require payment in advance,
based on detailed C4 estimates, in order to get them to
commit to the works and enable the Main Contractor to programme and
coordinate their individual on-site activities.
In accordance with Standing Order 5.8.1 (a) (i), the services are
proprietary, and no alternative provider is available.
These costs are refundable, should the scheme not proceed.
Zayo Group have submitted a C4 detailed estimate in the sum of
£81,585.29
Decision type: Non-key
Decision status: Recommendations Approved
Notice of proposed decision first published: 01/06/2023
Decision due: 31 May 2023 by Executive Director of Transport
Contact: John Dowie, Executive Director of Infrastructure and Place Email: john.dowie@southyorkshire-ca.gov.uk Email: John.Dowie@southyorkshire-ca.gov.uk.