Decision details

A630 Bus Improvements (Bus Priority Technology Upgrades)

Decision Maker: Corporate Director of Public Transport

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

Following approval of the Final Business Case, the A630 Bus Improvements TCF project is now in a position to advance to the delivery stage. This report seeks approval to grant authority to DMBC for the delivery of the A630 Bus Improvements project at an estimated cost £1,256,920

Decision:

Approval to pass on to DMBC a sum of £1,256,920 for the delivery of A630 Bus Improvement TCF Project in accordance
with the terms of the funding agreement.

Enter into a funding agreement with DMBC
for the delivery of the A630 Bus Improvements TCF Project.

Alternative options considered:

• Not to approve
• Approve SYMCA to grant authority to DMBC to deliver the A630 Bus Improvements Scheme at an estimated cost of £1,256,920

Publication date: 07/06/2022

Date of decision: 01/06/2022

Accompanying Documents: