Decision Maker: Corporate Director of Public Transport
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
To progress the Phase 1 scheme, it is
necessary to appoint a number of utility companies to carry out the
diversion of existing services and equipment affected by the
highway works. Each company will require payment in advance, based
on detailed C4 stage estimates, in order to get them to commit to
the works and enable the main contractor to programme and
coordinate their individual on-site activities.
These services are proprietary, and no alternative provider can
carry them out.
The costs are refundable should the scheme not proceed.
SMT previously approved a sum of £65,954.00 for Northern
Powergrid in April 2022 but this figure excluded any
builders’ work which comprises all the trenching, ducting and
the like.
Northern Powergrid have therefore now provided a revised C4
estimate for the complete works in the sum of
£130,962.00.
Approved the appointment of Northern Powergrid
to carry out underground service diversions at a revised cost of
£130,962.00.
Background documents: Report from Director of Public Transport
Development taken to the 06 July 2022 Public Transport Team
meeting
Northern Powergrid C4 Estimate.
No alternative options are
available.
Publication date: 11/07/2022
Date of decision: 06/07/2022