Decision Maker: Corporate Director of Public Transport
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
The A633 forms a major transport link between
the Dearne Valley and Rotherham Town Centre and experiences
congestion around the Parkgate Shopping area. Alongside the new
road proposed to run from the A6123 Aldwarke Lane to both the rear
of Parkgate Shopping and a new park and ride facility serving tram
train, a complimentary scheme is proposed to widen the south entry
and exits from Taylors Lane roundabout. Modelling has shown the two
interventions will decongest the A633, improving journey time
reliability.
The Full Business Case was submitted on 13 of December 2021 and was
approved at the MCA meeting on 21 March 2022 subject to certain
conditions which the project team are currently working on to
discharge prior to execution of the contract by both parties.
To enable the roundabout widening works to be undertaken several
utilities companies have indicated they have apparatus which
requires alteration.
To progress the Taylors Lane approach widening scheme, it is
necessary to appoint a number of utility companies to carry out
diversion works for all existing services and equipment affected by
the highway works. Each company will require payment in advance,
based on detailed C4 estimates, in order to get them to commit to
the works and enable the Main Contractor to programme and
coordinate their individual on-site activities.
In accordance with Standing Order 5.8.1 (a) (i), the services are
proprietary, and no alternative provider is available.
The following C4 estimates have been received from those companies
with affected equipment:
Open Reach (BT) £204,633.35
Virgin Media £88,522.28
Approved the appointment of Open Reach and
Virgin Media to carry out underground service diversions at a cost
of £204,633.35.92 and £88,522.28
respectively.
The statutory undertaker’s apparatus
needs to be moved / diverted to allow the scheme to progress due to
the widening of the road and the new alignment of the kerblines.
The cables are owned by the respective companies and there is no
option other than the service provider relocating them.
Publication date: 11/07/2022
Date of decision: 06/07/2022
Accompanying Documents: