Decision details

Enhancements to Travel South Yorkshire Website

Decision Maker: Section 73 Officer

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

The current maintenance/support period for Veeam is due to end in February 2023

Decision:

Option 3, at a cost of £54,945.05 via direct award to Insight using the HealthTrust Europe’s (HTE’s) ICT Solutions 2019 Framework which SYPTE are signed up to use and have used it previously.

Alternative options considered:

The options considered were:

1. Do Nothing - The Travel South Yorkshire (TSY) Website would continue in the current form with the associated inherent issues around performance and appearance.

2. Full Redevelopment - This was decided to be the longer term plan for the TSY Website and is part of the organisations whole website strategy for the future.

3. Make changes where they would have the most immediate
impact - This is the chosen option were resources and time
can be more focused on providing a better experience for users of the TSY Website

Publication date: 17/01/2023

Date of decision: 17/01/2023

Accompanying Documents: