Decision Maker: Executive Director of Transport
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
To mitigate against failure of bridge bearing
connection on Commercial Street Bridge.
The Commercial Street (Bow String) bridge forms a key link on the
Supertram network linking Sheffield City Centre to the east part of
the network, Meadowhall, Halfway and Herdings Park, including the
tram depot.
As part of their routine inspections SYSL has identified a
structural failure in the connection between the fixed bearing and
the bridge superstructure requiring immediate analysis and repair
work.
The structure is owned by SYMCA and will also be SYMCA operational
responsibility in March 2024 and as such need to determine and
implement a repair.
SYSL continues to monitor the defect for deterioration.
Appoint Balfour Beatty to progress the
Pre-Construction Phase including detail design of Commercial Street
Bridge at a cost of £92,329.42 through the SCAPE
framework.
Option 1
Do nothing :- The cause of the local failure is believed to have
been caused by thermal expansion of the bridge superstructure and
repeat of the circumstances which caused the failure (temperatures
circa 40 deg C or above) could lead to further damage and potential
closure of the structure on safety grounds, isolating the city
centre and west part of the tram network for the depot and east
part of the tram network, therefore cessation of tram services west
of Park Square roundabout.
Option 2
Progress a repair solution through a combination of consulting
engineers and contractors :- discounted due to timescales in
procuring consultants and then when a preferred solution has been
determined a suitable contractor procurement would further prolong
the repair programme.
Option 3
Utilise the existing SCAPE framework to appoint Balfour Beatty to
progress a Design and Build Contract to first analyse and determine
a preferred solution and then implement.
SYMCA is signed up to the SCAPE framework and therefore compliance
with procurement requirements is met.
The appointment of Balfour Beatty brings in the construction
element as part of one appointment and as part of the SCAPE
framework process, free programming services and initial works cost
estimation are provided prior to entering into the works
contract.
Prior to the works contract SYMCA was required to enter into a two
stage analysis and design phase.
The analysis work cost £68,330.83 and reviewed the problem
and presented the preferred option for client approval (AIP). This
is now required to be taken to a detailed design prior to
construction commencing.
The detail design element incorporating additional works to
mitigate against the thermal expansion of the superstructure
causing issues in the future in included in the Pre-Construction
Phase and has increased from the commencement estimate of
£70,000 to £92,329.42 as a result of this.
The overall estimated works cost is circa £850,000, including
the additional mitigation works at the western end of the bridge
away from the initially identified issue.
Publication date: 21/05/2024
Date of decision: 20/05/2024
Accompanying Documents: