Decision Maker: Section 73 Officer
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Barnsley Council proposes to implement a
three-phase project to secure the Alhambra as a viable and
sustainable economic asset for Barnsley town centre.
The delivery of the project requires Barnsley Council to draw down
a maximum of £63m of its SY Gainshare allocation over the
period 2024-2050: This is made up of £36m capital to deliver
Phases 1 and 2 and up to £29m revenue to finance the interest
payments.
The OBC was approved Sep-23, with draw down of development grant
(£4.6m) approved at Programme Board Apr-24.
BMBC have requested a further £1.25m development funding to
be released to fund their continued investment as the project
progresses (uplift the release of development cost funding from
£4.6m to £5.85m).
Approval of change control for D0063 Health on
the High Street and award of an additional £1.25m development
grant to Barnsley Metropolitan Borough Council.
Option 1
Approve the recommendation
Option 2
Reject the recommendation
Publication date: 27/06/2024
Date of decision: 26/06/2024