The project has now reached the Project
Delivery phase and investment authority is now required to appoint
Network Rail to undertake construction of the new station. The
appointment will be formalised with the signing of an
Implementation Agreement with Network Rail setting out the terms
and conditions of the appointment at a budget ceiling of
£6,859,649.
Subject to approval of this report and a timely transition to the
construction stage, with all necessary contracts signed and in
place, it is planned to make a start on site Spring 2024 with
forecast completion and entry into service Autumn/Winter
2024.
Decision type: Key
Reason Key: Both;
Decision status: Recommendations Approved
Notice of proposed decision first published: 12/02/2024
Decision due: 7 Feb 2024 by Executive Director of Transport
Contact: Pat Beijer, Director of Transport and Capital Delivery Email: pat.beijer@southyorkshire-ca.gov.uk Email: pat.beijer@southyorkshire-ca.gov.uk.