A scalable bus improvement project which will
deliver bus priority along the A61 corridor from Meadowhead
roundabout in the South to Sheffield city centre in the
north.
The project was originally approved in Feb-23 under the old
framework, and SCC has claimed development grant of £250k in
full. There has since been some movement in the expected submission
date of the business case due to the preparatory work
involved.
SCC request further upfront development grant be released to aid
progress of the project. The request results in 14% (£1.4m)
of the total costs being drawn down during development.
Decision type: Non-key
Decision status: Recommendations Approved
Notice of proposed decision first published: 27/06/2024
Decision due: 26 Jun 2024 by Section 73 Officer
Contact: Gareth Sutton, Executive Director of Resources & Investment Email: charli.taylor@southyorkshire-ca.gov.uk Email: Gareth.Sutton@southyorkshire-ca.gov.uk.