To progress the Phase 1 scheme, it is
necessary to appoint a number of utility companies to carry out the
diversion of existing services and equipment affected by the
highway works. Each company will require payment in advance, based
on detailed C4 stage estimates, in order to get them to commit to
the works and enable the main contractor to programme and
coordinate their individual on-site activities.
These services are proprietary, and no alternative provider can
carry them out.
The costs are refundable should the scheme not proceed.
SMT previously approved a sum of £65,954.00 for Northern
Powergrid in April 2022 but this figure excluded any
builders’ work which comprises all the trenching, ducting and
the like.
Northern Powergrid have therefore now provided a revised C4
estimate for the complete works in the sum of
£130,962.00.
Decision type: Non-key
Decision status: Recommendations Approved
Notice of proposed decision first published: 11/07/2022
Decision due: 6 Jul 2022 by Corporate Director of Public Transport
Contact: Stephen Edwards, Corporate Director of Public Transport Email: stephen.edwards@southyorkshire-ca.gov.uk Email: stephen.edwards@southyorkshire-ca.gov.uk.